Transition of project
Once project is awarded, the following items are needed from the Estimator prior to transitioning project to Preconstruction and Project Management.
Set up a meeting to fully explain all the intricate details of the project.
Owner contact information (Corecon)
Project address (CoreCon)
Final copy of plans and contract specifications (CoreCon)
Copy of the executed contract / Scope of Work (CoreCon)
Budget / Estimate review- Review any changes in proposal with Project Manager/ Pre-Con.
Special notes relating to the project during the Sales / Estimating
Copies / access to any RFI during the bid process (CoreCon)
Provide tentative start date- Biz Dev
List of specialty lead time items
List any preferred trade partners for project (i.e. customer trade partner relation, trade partner preference on project)- Director of Pre-Construction
Site access special concerns
Design team information
PROJECT HANDOVER FROM SALES TO PROJECT MANAGER
ALL REQUIRED
Meeting to include salesman, Estimator, Director of Pre-Con, Project Manager, and Superintendent.
Owner contact person for Project Manager and Superintendent
Project address.
Final Copy of plans. Need the date of the most recent set of plans (CoreCon)
Review plans in the turnover meeting to review notes / special conditions, differences in bid plans vs Executed plans, etc.
A detailed review of MEP drawings for equipment, ductwork, electrical outlets, etc.
Copy of the Executed contract /proposal.
Review the Scope of work in detail to understand what's included/ excluded.
Review the estimate / budget line by line with a description of the work.
Review photos and video walkthroughs completed thus far.
Copies of any special notes relating to the project
Copies / access to any RFI’s during the bid process
Review notes/anything that was promised to the client.
Provide a tentative start date, (can be quarterly/year)
A list of any specialty / long lead items
List any preferred trade partners for the project, (i.e. customer trade partner relation, trade partner preference on the project)
Site access concerns
Design team information if any
All of the above information shall be stored in our Estimating folder and a Handover Document needs to be created for this process, which will be filled out in the meeting.